Progress bar updates

Juan Carlos Gonzalez-Najera's Avatar

Juan Carlos Gonzalez-Najera

10 Jul, 2009 05:02 PM via web

I have been adding tasks to shots, and I have begun adding % completion to each task. However, the sequences that the shots are part of still show progress of 0%.

What triggers sequence % completion updates?

Juan Carlos

  1. Support Staff 2 Posted by cameron on 10 Jul, 2009 05:09 PM

    cameron's Avatar

    For sequences, the % complete is simply a function of the number of shots that are completed (it is labeled "Shots Complete".)

    We don't use a sum or average of the tasks complete for all shots in a sequence because people are not very consistent about creating all the tasks for all the shots that are needed to complete a sequence, thus, the % complete would be meaningless 99% of the time.

    What I would like to do, is show some kind of per-shot progress indicator, perhaps showing dates or or a graph of the operations needed on a shot. Figuring out exactly what this should look like has been daunting.

  2. cameron closed this discussion on 10 Jul, 2009 05:09 PM.